House cleared of positive materials before demolition, with the survey in the application
Example project
- Home
- 1950s house of about 1,100 sq ft in Bellflower
- Original request
- Take the house down and build a new one on the lot
- Testing
- A comprehensive survey of the whole building by a Cal/OSHA-certified asbestos consultant, about 18 samples from ceilings, floors, walls and the furnace closet
- Found
- Asbestos in the ceiling texture, the kitchen and bath flooring and the wall compound
- Clear
- The garage walls
- Area
- About 1,000 sq ft of ceiling, 280 sq ft of floor and 350 sq ft of wall
- Timeline
- Notice no later than 10 working days ahead, then five working days before the wrecking crew
- Cost
- $16,500
In this example, an owner in Bellflower is replacing a 1950s house. The city requires each demolition application to come with a comprehensive asbestos survey and the Rule 1403 paperwork, so both are in hand before the application goes in.